Collection System Improvements Contract 2 - Week of April 7th
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Late February, contractor mobilize to Park Avenue Siphon Chamber
Work Period & Location
Week of April 7th
Intersection of Park Ave and JFK Blvd E in Weekawken
Description of Work
Installing a 24” gate valve and activating the Park Avenue Siphon Chamber
Traffic Information:
Road Closures: Applicable roads will be closed overnight by police for the duration of active work at that location.
Parking Restrictions: None
Detours: Traffic will be reduced to a single lane in each direction during active construction.
Police presence: Yes, assisting with street closures as noted above.
Additional Notes:
Work will resume on Monday at the Park Avenue location to restore the site; total duration 2-3 days.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!