Collection System Improvements Contract 2 - Week of April 7th

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Late February, contractor mobilize to Park Avenue Siphon Chamber

Work Period & Location

  • Week of April 7th

  • Intersection of Park Ave and JFK Blvd E in Weekawken

Description of Work

  • Installing a 24” gate valve and activating the Park Avenue Siphon Chamber

Traffic Information:

  • Road Closures: Applicable roads will be closed overnight by police for the duration of active work at that location.

  • Parking Restrictions: None

  • Detours: Traffic will be reduced to a single lane in each direction during active construction.

  • Police presence: Yes, assisting with street closures as noted above.

Additional Notes:

  • Work will resume on Monday at the Park Avenue location to restore the site; total duration 2-3 days.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!