NHSA Grand Street Interceptor and Pump Station Feasibility Study - Traffic Management Week of 10/9/23

Find the traffic plan for the soil boring work we have planned.  A description of the work and the traffic management can also be found below.

Tuesday, 10/10/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-22) at the southwest end of Grand Street where it meets 11thStreet.

  • Grand Street between 11th street and 12th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the southwest end of Grand Street where it meets 11th Street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Wednesday, 10/11/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-22) at the southwest end of Grand Street where it meets 11thStreet.

  • Grand Street between 11th street and 12th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the southwest end of Grand Street where it meets 11th Street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Thursday, 10/12/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-21) at the northwest end of Grand Street where it meets 11thStreet.

  • Grand Street between 10th street and 11th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northwest end of Grand Street where it meets 11th Street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Friday, 10/13/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-20) at the southwest end of Grand Street where it meets 10thStreet.

  • Grand Street between 10th street and 11th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the southwest end of Grand Street where it meets 10th Street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

Previous
Previous

NHSA Grand Street Interceptor And Pump Station Feasibility Study - Traffic Management Week Of 10/16/23

Next
Next

NHSA Weehawken Infrastructure Project Two Week Look Ahead For 10/2 - 10/13/2023