NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: March 3 – March 7, 2025
Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.
Key Phases & Timeline
Week of March 3 – March 7, 2025
Work Locations:
13th Street between Adams and Jefferson Streets
Adams Street between 13th and 15th Streets
Construction Activities
Working on Stairs, Grating and Prepping for Louvers at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets
Installation of light pole bases, bollards, watermain and concrete curb and sidewalk work under viaduct at 14th and Adams
Traffic Management
Grand Street is now opened both ways until the contractor performs the wet tapping valve installation. Estimated ship date for tapping sleeve is 2/27/2024 will arrive beginning of March. Anticipated construction 2nd week in March.
Adams Street between 13th and 15th Streets will be closed to thru traffic, but open to thru traffic at night.
HPD officers will be present at all intersections.
24/7 no parking signs will be in place on both sides of Adams Street between 13th and 15th Streets.
There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.
We appreciate your patience and cooperation as we work to improve our infrastructure.