NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: March 10 – March 14, 2025
Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.
Key Phases & Timeline
Week of March 10 – March 14, 2025
Work Locations:
13th Street between Adams and Jefferson Streets
Adams Street between 13th and 15th Streets
Construction Activities
Working on stairs, grating, and prepping for louvers at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets
Restoration of granite curb, concrete curb, concrete sidewalk, and bollards under the viaduct at the intersection of 14th and Adams Streets
Restoration of concrete curb and sidewalk on Adams Street between 13th and 15th Streets in front of local buildings
Contractor will be working on excavation and placement of wet tap at 15th Street between Clinton Street and Willow Avenue, from 3/10/2025 thru 3/14/2025. Contractor estimates one week to perform the wet tap and one week to connect. The connection will take place on 3/17/2025 to 3/21/2025.
Traffic Management
Adams Street between 13th and 15th Streets will be closed to thru traffic, but open to thru traffic at night.
HPD officers will be present at all intersections.
24/7 no parking signs will be in place on both sides of Adams Street between 13th and 15th Streets.
There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.
15th Street between Clinton Street and Willow Avenue will have one-way westbound thru traffic from 3/10 thru 3/14. Roadway will be open to thru traffic during weekends.
We appreciate your patience and cooperation as we work to improve our infrastructure.