NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 11/4/2024 through 11/8/2024
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 11/4/2024 through 11/8/2024 as follows:
Holiday
11/5/2024 – Election Day – No Work
Construction Activities
National Watermain Investigation of Trunk Sewer on 15th Street from Adams to Grand Street.
Investigation consists of cleaning and performing joint repairs
Concrete and Internal Piping Work at the NWRP Pump Station on 13th Street between Adams and Jefferson Street.
Installation of Force-main and Gravity Sewer on Adams Street between 13th and 14th Street.
Installation of Concrete Piers and Pile caps on Adams Street between 13th and 14th Street.
Traffic Management
HPD Officers will be present on site to assist in traffic redirection at all construction locations.
No parking signs will be placed on both sides of 15th Street between Adams Street and Grand Street.
No parking signs will be placed on both sides of Adams Street Between 13th and 14th Street.
There may be partial impacts to the sidewalks on 13th Street between Adams and Jefferson Streets within the pump station work area. Be mindful of Impacts.
Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day.