NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 11/4/2024 through 11/8/2024

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 11/4/2024 through 11/8/2024 as follows:

 

Holiday

11/5/2024 – Election Day – No Work

 

Construction Activities

  • National Watermain Investigation of Trunk Sewer on 15th Street from Adams to Grand Street.

    • Investigation consists of cleaning and performing joint repairs

  • Concrete and Internal Piping Work at the NWRP Pump Station on 13th Street between Adams and Jefferson Street.

  • Installation of Force-main and Gravity Sewer on Adams Street between 13th and 14th Street.

  • Installation of Concrete Piers and Pile caps on Adams Street between 13th and 14th Street.  

 

Traffic Management

  • HPD Officers will be present on site to assist in traffic redirection at all construction locations. 

  • No parking signs will be placed on both sides of 15th Street between Adams Street and Grand Street. 

  • No parking signs will be placed on both sides of Adams Street Between 13th and 14th Street.

  • There may be partial impacts to the sidewalks on 13th Street between Adams and Jefferson Streets within the pump station work area. Be mindful of Impacts. 

  • Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day.

Previous
Previous

NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 11/11/2024 through 11/15/2024

Next
Next

NHSA H6/H7 Phase 2: Construction and Traffic Management Activities in Hoboken 10/28/2024 through 11/1/2024