NHSA - Port Imperial Pump Station No. 3 Rehabilitation
Week-by-Week Overview of Project Phases and Timelines
Week 1: Thursday, 1-18 and Friday 1-19, the Contractor will mobilize to the site, which include the delivery of equipment.
Week 2: 1-22 to 1-26 the Contractor will begin setting up the by-pass pumps. On Tuesday 1-23 and Wednesday, 1-24, the Contractor will be excavating in Port Imperial Boulevard to install the by-pass piping. The roadway will be reopened at the end of each shift.
Week 3: 1- 29 to 2-1 the Contractor will put the pumping station on by-pass and work around the clock to complete the work inside of the pumping station. The work will not involve excavation but the Contractor will have light tower set-up. The work is scheduled to take 5-days.
Week 4: 2-4 to 2-8 the Contractor will demobilize and remove materials and equipment. They will also have to work within Port Imperial Boulevard.