North Hudson Sewerage Authority H6/H7 Phase 2: Hoboken's Traffic Management and Construction Activities Update (March 25, 2024 - March 29, 2024)

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 03/25/2024 through 03/29/2024 is as follows:

 

Construction Activities

  • Watermain relocation on Adams and 14th Street and Adams and 15th Street.

  • Electric and Telecommunication relocation on Adams and 14th Street.

 

Traffic Management

  • Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day from 3/25 thru 3/28.

  • 2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 13th, and one will be located at 15th.

  • No parking signs will be placed on both sides of Adams Street between 14th Street and 15th Street from 3/25 thru 3/28.

  • There may be partial impacts to the sidewalks on 13th and Adams, 14th and Adams, and 15th and Adams in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

  • 15th Street and Adams Street will have two lane shift to the South Side while the Contractor works on the North side.

  • 2 HPD Officers will be present on site to assist in traffic on 15th Street.

  • No parking signs will be placed on both sides of 15th Street between Grand Street and Adams Street on 3/28 thru 3/29.

  • There may be partial impacts to the sidewalks on 15th and Adams in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project: Two Week Look Ahead for April 1st to April 12th, 2024

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead From March 25 to April 5, 2024