Adams Street Wastewater Treatment Plant Influent Force Main and Siphon Repair - Week of Feb 17th
Purpose of Project:
This infrastructure rehabilitation project aims to improve safety, reliability, and efficiency by upgrading aging systems. It will extend the lifespan of critical infrastructure, reduce maintenance needs, and enhance service for the community.
Location:
📍 Intersection of Park Ave and JFK Blvd E, Weehawken
Work Details:
Installing a 24” gate valve and activating the Park Avenue Siphon Chamber
Traffic Information:
Single lane in each direction on Park Ave during construction
Police presence by Township of Weehawken
Community Impacts:
Noise from heavy equipment during excavation
Key Phases/Timeline:
Late February – Contractor mobilizes to Park Avenue Siphon Chamber
Early April – Completion of siphon rehabilitation