NHSA H6/H7 Hoboken Phase 2: Construction and Traffic Management Activities 02/17/2025 through 02/21/2025
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 Project for the period of 02/17/2025 through 02/21/2025 is as follows:
Holiday
02/17/2025 – Presidents Day – No Street Work for Contractor
Construction Activities
Working on Stairs, Grating and Prepping for Louvers at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets
Installation of Catch Basins on Adams Street between 14th and 15th Streets
Installation of Concrete Piers and Pile Caps on 15th between Grand Street and Clinton Street
Traffic Management
Grand Street is now opened as work at the intersection is completed and paved.
15th Street between Grand and Clinton Streets will have one-way westbound traffic, eastbound traffic will be detoured on 16thStreet
15th and Clinton Street intersection will be closed, and traffic will be detoured south on Grand Street and east on 14th Street.
HPD officers will be present at the intersections of 15th and Grand Streets and 15th and Clinton Streets to allow local traffic to access to both streets.
HPD Officers will be present on site to assist in traffic redirection at all construction locations.
14th Street between Clinton and Grand Streets will be open to westbound thru traffic.
Adams Street between 14th and 15th Streets will be open to thru traffic at night
15th Street will have one-way westbound traffic for all vehicles.
24/7 no parking signs will be in place on both sides of Adams Street between 14th and 15th Streets.
There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson within the pump station work area.