NHSA H6/H7 Phase 2 - Construction and Traffic

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 02/12/2024 through 02/16/2024 is as follows:

 

Construction Activities

  • Watermain relocation on Adams Street between 13th Street and 14th Street. 

Traffic Management

  • 13th Street between Grand and Adams will be closed to thru traffic during the day on 2/12 and 2/13. 

  • 2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 13th and Grand and one will be located at 13th and Adams. 

  • No parking signs will be placed on both sides of 13th Street between Willow Street and Clinton Street on 2/12 and 2/13.

  • Adams Street between 13th and 14th Street will be closed 2/12 thru 2/16. 

  • 1 HPD Officer will be present at 13th and Adams Street to assist in traffic redirection.

  • No parking signs will be placed on Adams from 13th Street to 14th Street on 2/12 thru 2/16.

  • There may be partial impacts to the sidewalks on 13th and Adams in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

 

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead For 2/19- 3/1/2024

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead For 2/12 - 2/123/2024