Construction Activities and Traffic Management for NHSA H6/H7 Phase 2 Project: June 3 - June 7, 2024


Here are the anticipated Construction Activities and Traffic Management details for the NHSA H6/H7 Phase 2 project for the period 6/3/2024 through 6/7/2024:

Construction Activities

  • Test Pits

    • 15th & Grand Street

    • 15th & Clinton Street

  • Installing Helical Anchors

    • 15th Street between Adams Street and Grand Street

      • Note: Contractor will be using an excavator to install the anchors. Contractor will be performing noise monitoring throughout the work.

    • 15th Street between Grand Street and Clinton Street

      • Note: Contractor will be using an excavator to install the anchors. Contractor will be performing noise monitoring throughout the work.

Traffic Management

  • 15th Street between Adams Street and Grand Street

    • Two-lane traffic from 6/3. Traffic will be shifted to the North Side of 15th Street.

    • No parking signs will be placed on both sides from 6/3 through 6/4.

    • 2 HPD Officers will be present on site to assist in traffic redirection:

      • One located at Adams and 15th Streets

      • One located at Grand and 15th Streets

    • Grand Street between 15th Street and 14th Street will be closed to traffic on 6/3.

    • There may be periods of alternating traffic, which officers will assist with.

    • There may be partial impacts to sidewalks; however, safe passage for pedestrian traffic will be provided at all times.

  • 15th Street between Grand Street and Clinton Street

    • Two-lane traffic from 6/3 through 6/7. Traffic will be shifted to the North Side of 15th Street.

    • No parking signs will be placed on both sides from 6/3 through 6/7.

    • 2 HPD Officers will be present on site to assist in traffic redirection:

      • One located at Clinton and 15th Streets

      • One located at Grand and 15th Streets

    • Clinton Street between 15th Street and 14th Street will be closed to traffic on 6/3.

    • There may be periods of alternating traffic, which officers will assist with.

    • There may be partial impacts to sidewalks; however, safe passage for pedestrian traffic will be provided at all times.

We appreciate your patience and cooperation as we work to improve our wastewater infrastructure.

Previous
Previous

NHSA H6/H7 Phase 2 project's construction activities and traffic management in Hoboken from June 10th to June 14th, 2024

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project: Two-Week Look Ahead for June 3 - June 14, 2024