Madison Street Infrastructure Improvements: Construction and Traffic Management Activities March 17th - 21st
Madison Street Infrastructure Improvements
The Madison Street Area Infrastructure Improvements project will help mitigate localized flooding from rain events. The project scope includes replacing existing inlets, sewers, and water lines as well as elevating roadways, curbs, and sidewalks within the area. These improvements will alleviate the primary concerns by conveying stormwater into the sewer system.
Work on the Madison Street Area Infrastructure Improvements will require parking restrictions, partial road closures, and 24-hour closure of Madison. Area residents will be kept apprised of the work and impacts on their quality of life.
The following work and traffic management activities are anticipated for Monday, March 17th through Friday, March 21st between the hours of 8 a.m. and 4 p.m.:
Work Activities:
Madison St between 10th and 11th Street
Maintain Sewer Bypass
Excavate and Install Pile Caps
Install New Watermain and Sewer Main
Install Sewer Manhole 761.
Reconnect lateral pipes.
Complete tie in of new 42” sewer to the at 11th St.
Traffic Management:
Madison St full closure between 10th and 11th Street.
No-Parking on Madison St between 10th and 11th Street.
HPD will be on-site to assist with traffic management during construction.