NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: March 17 – March 21, 2025

Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.

Key Phases & Timeline

  • Week of March 17 – March 21, 2025

  • Work Locations:

    • 13th Street between Adams and Jefferson Streets

    • Adams Street between 13th and 15th Streets

Construction Activities

  • Working on louvers and pipe rails for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets

  • Installation of bollards, concrete curb and sidewalk work under viaduct at the intersection of 14th and Adams Street

  • Finalizing wet tap and tie-in at the intersection of 15th and Clinton Streets

  • Installation of final connection to wet tap on 15th Street between Willow and Clinton Streets

Traffic Management

  • Clinton Street will be one-way thru traffic due to Wet Tap Connection within the intersection.

  • Adams Street between 13th and 15th Streets will be closed to thru traffic for Curb and Sidewalk, but open to thru traffic at night.

  • 15th Street will have one-way traffic going westbound to Clinton Street.

  • HPD officers will be present at all intersections. 

  • 24/7 no parking signs will be in place on both sides of Adams Street between 13th and 15thStreets.

  • There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.

We appreciate your patience and cooperation as we work to improve our infrastructure.

Previous
Previous

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities March 24th - 28th

Next
Next

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities March 17th - 21st