Find the traffic plan for the soil boring work we have planned.  A written description of the work and the traffic management can also be found below.

Monday, 10/2/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-26) at the northwest end of Grand Street where it meets 14th Street.

  • Grand Street between 13th street and 14th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northwest end of Grand Street where it meets 14thStreet will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Tuesday, 10/3/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-25) at the southwest end of Grand Street where it meets 13th Street.

  • Grand Street between 13th street and 14th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the southwest end of Grand Street where it meets 13thStreet will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Wednesday, 10/4/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-24) at the southwest end of Grand Street where it meets 12th Street.

  • Grand Street between 12th street and 13th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the southwest end of Grand Street where it meets 12thStreet will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Thursday, 10/5/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-24) at the southwest end of Grand Street where it meets 12th Street.

  • Grand Street between 12th street and 13th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the southwest end of Grand Street where it meets 12thStreet will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Friday, 10/6/2023

  • Craig Testing will be on-site with a drilling rig to take a soil boring (B-23) at the northwest end of Grand Street where it meets 12th Street.

  • Grand Street between 11th street and 12th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northwest end of Grand Street where it meets 12thStreet will be closed by the Parking Authority for the day, to allow the construction work to be performed.