NHSA Grand Street Interceptor and Pump Station Feasibility Study - Traffic Management Week of 11/13/23

Please find the written description of the traffic plan for the soil boring work, along with the project and traffic management details provided below.

Monday, 11/13/2023

  • Craig Testing will be on-site with a drilling rig to drill Environmental Temporary Wells (TWP-6 and TWP-7) at the northwest end of Grand Street where it meets 16th Street and the southwest end Grand Street where it meets 13th Street.

  • Grand Street between 13th-14th street and 15th-16th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northwest end of Grand Street where it meets 16th Street and the southwest end of Grand Street where it meets 13th street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Tuesday, 11/14/2023

  • Craig Testing will be on-site with a drilling rig to drill Environmental Temporary Wells (TWP-4 and TWP-5) at the northwest end of Grand Street where it meets 12th Street and the southwest end Grand Street where it meets 8th Street.

  • Grand Street between 8th-9th street and 11th-12th street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northwest end of Grand Street where it meets 12th Street and the southwest end of Grand Street where it meets 8th street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Wednesday, 11/15/2023

  • Craig Testing will be on-site with a drilling rig to drill Environmental Temporary Wells (TWP-2 and TWP-3) at the southwest end of Grand Street where it meets 6th Street and the southwest end Grand Street where it meets 2nd Street.

  • Grand Street between 5th-6th street and 2nd-3rd street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only.  

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northwest end of Grand Street where it meets 6th Street and the southeast end of Grand Street where it meets 2nd street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

 

Thursday, 11/16/2023

  • Craig Testing will be on-site with a drilling rig to drill Environmental Temporary Wells (TWP-1) at the southwest end of 1st Street where it meets Madison Street.

  • 1st Street between Madison Street and Monroe Street will be closed to through traffic between the hours of 9:00 am to 4:00 pm.

  • One lane on Grand Street will be maintained open for local traffic only

  • A uniformed police officer will be present to direct local traffic around the construction work.

  • Several parking spots at the northeast end of 1st Street where it meets Madison Street will be closed by the Parking Authority for the day, to allow the construction work to be performed.

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead For 11/20- 11/24/2023

Next
Next

NHSA Grand Street Interceptor and Pump Station Feasibility Study - Traffic Management Week of 11/6/23