NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 08/19/2024 through 08/23/2024

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 08/19/2024 through 08/23/2024 is as follows:

 

Construction Activities

  • Working inside the Control Building and Wet Well Chamber – 13th Street between Adams and Jefferson South Side

    • Note: Thru traffic will still be allowed, as work will be done off the road.

 

Traffic Management

  • 13th Street between Adams and Jefferson will be open to thru traffic from 8/19 to 8/23.

  • No officers required.

  • No parking signs will be placed on both sides of 13th Street between Adams and Jefferson from 8/19 to 8/23.

  • There may be partial impacts to the sidewalks on 13th Street between Adams and Jefferson in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

Previous
Previous

NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 08/26/2024 through 08/30/2024

Next
Next

NHSA H6/H7 Phase 2 - Construction and Traffic Management Activities 08/05/2024 through 08/09/2024