Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 10/07/2024 through 10/11/2024 is as follows:
Construction Activities
Pump Station Installation – No traffic Impact
Force Main and Gravity Sewer Pipe Installation – Adams Street between 13th and 14th Streets
Traffic Management
Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day from 10/7 thru 10/11.
2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 13th Street, and one will be located at 14th Street.
No parking signs will be placed on both sides of Adams Street between 13th Street and 14th Street from 10/7 thru 10/11.
24/7 No Parking Both Sides on Adams Street between 13th Street and 14th Street from 10/7 thru 10/11.
There may be partial impacts to the sidewalks on Adams between 13th and 14th Streets in the Work area, however, safe passage for pedestrian traffic will be provided at all times.