NHSA H6/H7 Phase 2: Hoboken Construction and Traffic Management Activities 10/14/2024 through 10/18/2024
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 10/14/2024 through 10/18/2024 is as follows:
Holiday
10/14/2024 – Columbus Holiday – No Work
Construction Activities
Pipe Installation, Catch Basin Installation – Adams Street between 13th and 15th Streets
Investigation of Trunk Sewer on 15th Street between Jefferson and Adams Streets
Work at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets
Traffic Management
Adams Street between 13th Street and 15th Street will be closed to thru traffic during the day from 10/15 thru 10/18.
2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 13th Street, and one will be located at 15th Street.
No parking signs will be placed on both sides of Adams Street between 13th Street and 15thStreet from 10/15 thru 10/18.
No parking signs will be placed on the south side of 15th Street between Jefferson and Adams Streets from 10/16 thru 10/18.
24/7 No Parking Both Sides on Adams Street between 13th Street and 15th Street from 10/15 thru 10/18.
There may be partial impacts to the sidewalks on Adams Street between 13th and 15thStreets in the Work area, however, safe passage for pedestrian traffic will be provided at all times.