NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 11/18/2024 through 11/22/2024
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 11/18/2024 through 11/22/2024 is as follows:
Construction Activities
National Watermain Investigation of Trunk Sewer on 15th Street from Adams to Grand Street suspended by contractor until further notice – Police Cancelled
Concrete and Internal Piping Work at the NWRP Pump Station on 13th Street between Adams and Jefferson Street. Ongoing no changes.
Installation of Force-main and Gravity Sewer on Adams Street between 13th and 14th Street. Ongoing no changes.
Installation of Concrete Piers and Pile caps on Adams Street between 13th and 14th Street. Ongoing no changes.
Test Pitting on 15th Street and Clinton Ave Contractor to Determine Spacing at Tapping Location
Traffic Management
HPD Officers will be present on site to assist in traffic redirection at all construction locations. Ongoing no changes.
No parking signs will be placed on both sides of 15th Street between Clinton and Willow.
No parking signs will be placed on both sides of Adams Street Between 13th and 14th Street. Ongoing No Changes.
There may be partial impacts to the sidewalks on 13th Street between Adams and Jefferson Streets within the pump station work area. Be mindful of Impacts. Ongoing no Changes.
Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day. Ongoing No Changes.