NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 11/25/2024 through 11/29/2024
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 11/25/2024 through 11/29/2024 is as follows:
Holidays
11/28/2024 – Thanksgiving Day – No Work for Contractor
11/29/2024 – Day after Thanksgiving – No Work for Contractor
Construction Activities
National Watermain Activities Suspended Until further Notice. No Police.
Concrete and Internal Piping Work at the NWRP Pump Station on 13th Street between Adams and Jefferson Street. Ongoing no changes.
Installation of Force-main and Gravity Sewer on Adams Street between 13th and 14th Street. Ongoing no changes.
Installation of Concrete Piers and Pile caps on Adams Street between 13th and 14th Street. Ongoing no changes.
Traffic Management
HPD Officers will be present on site to assist in traffic redirection at all construction locations. Ongoing no changes.
No parking signs will be placed on both sides of 15th Street between Clinton and Willow Operation Complete Signs Removed.
No parking signs will be placed on both sides of Adams Street Between 13th and 14th Street. Ongoing No Changes.
There may be partial impacts to the sidewalks on 13th Street between Adams and Jefferson Streets within the pump station work area. Be mindful of Impacts. Ongoing no Changes.
Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day. Ongoing No