Anticipated Construction Activities and Traffic Management for the NHSA Newark and Observer Sewer Rehabilitation project for the period of 07/29/2024 through 08/02/2024 is as follows:

 

Work Zone 1 (North side of the Median)

  • Construction Activities: Tuesday 7/30 (8 AM – 4 PM) 

    • The Contractor will perform trench restoration with temporary pavement in both the road and the sidewalk

  • Traffic Control

    • The Contractor will utilize the same traffic control plan that is currently set up. 

    • No thru traffic on Newark Street between Adams and Madison St. 

    • West bound truck traffic to be detoured to Clinton St.

    • East Bound Truck Traffic to be detoured to Madison St.

    • Hoboken PD stationed at Madison and Adams to assist with traffic control.

    • VMS sign install at Madison St and Adams St. 

 

Work Zone 2 (South Side of the Median) 

  • Construction Activities: Wednesday 7/31 Thursday 8/1 (8 AM – 4 PM) and Friday 8/2 (8 Am – 1PM)

    • The Contractor will be performing test pits within Work zone 2 (south of the median) at Observer Highway and Henderson Street.

    • Once test pits are complete The Contractor will perform trench restoration with temporary pavement. 

    • Steel plates will be reinstalled over the existing sewer.

  • Traffic Control

    • No thru traffic (east and west bound) on Observer Highway at Henderson Street.

    • Westbound truck traffic to be detoured to Washington Street. 

    • Truck traffic cannot be detoured to Henderson Street due to bridge clearance south of the intersection.

    • All other westbound traffic to be detoured to Henderson Street. 

    • All Eastbound traffic shall be detoured to Madison Street. 

    • VMS Boards will be placed at Madison Street and Willow Ave. 

    • Hoboken PD will assist with Officers at Madison, Willow and Washington. 

    • The Contractor will attempt to  maintain westbound access for trucks only in the event they miss the detours at Washington and Willow.

Previous
Previous

NHSA H6/H7 Phase 2 - Construction and Traffic Management Activities 08/05/2024 through 08/09/2024

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week look ahead for 7/29 - 8/9/2024