North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week look ahead for 9/9 - 9/20/2024

There will be one crew working at the Highwood Ave Pump Station. The map below indicates the work areas and parking limitations.

 

Week 1: 9/9 - 9/13/2024

Hamilton Ave Pump Station Crew

Work at the pump station includes electrical and mechanical equipment work and generator pad concrete work.

 

House Keeping

· No vehicles, equipment, or materials will be stored on the sidewalk or in front of driveways.

· A temporary construction fence has been installed on the sidewalk in front of the parking lot and at the top of the stairs next to the lot.

· Traffic signs to be posted as necessary.

 

Week 2:

Generator placement and gas and electrical connections to the generator work will continue in week 2.

Upcoming schedule:

All major work outside of the pump station is complete.

Pump station work is in progress, and the conclusion of the pump station there will be final paving across the entire project site.

 

Completed work:

Work has been completed on Blvd East from 700 Blvd East to Hamilton Ave. A new 48” PVC combined sewer was installed along with manholes and new laterals and cleanouts. Highwood Ave is complete, with new stormwater piping separating sewer and stormwater from Blvd East to Hudson Place. A stormwater force main was installed on Highwood Ave and connected to the pump station. Hudson Place also had new stormwater and sewer piping along with new catch basins and manholes. The pump station structure has been installed at the pump station location and the force main connection has been made.

 

 

Highwood Ave / Pump Station Work


Previous
Previous

NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 09/09/2024 through 09/13/2024

Next
Next

NHSA H6/H7 Phase 2: Construction and Traffic Management Activities 08/26/2024 through 08/30/2024