Collection System Improvements Contract 2 - Week of March 31st

Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.

Key Phases & Timeline

  • Sewer cleaning and CCTV beginning March and continuing into April. Sewer lining beginning in April.

Work Period & Location

  • Week of March 31st

  • Night work 3/31-4/4, 830pm setup active 9pm thru 5am:
    - 12th Street between Morris St and up along Bergenline Ave to Tournade Lane
    - Bergenline Ave between 42nd and 43rd street
    - Bergenline Ave between 47th and 48th street

Description of Work

  • Cleaning and CCTV

Traffic Information:

  • Road Closures: Applicable roads will be closed overnight by police for the duration of active work at that location.

  • Parking Restrictions: None

  • Detours: Traffic will be reduced to a single lane in each direction during active construction.

  • Police presence: Yes, assisting with street closures as noted above.

Community Impacts

  • Noise/Disruptions: Sewer cleaning could produce some short duration noise.

We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!

Previous
Previous

NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: March 31st – April 4th, 202

Next
Next

Madison Street Infrastructure Improvements: Construction and Traffic Management Activities March 31st - April 4th