Collection System Improvements Contract 2 - Week of March 31st
Purpose of Project:
Rehabilitation of approximately 4,700 linear feet of combined sewers, manholes and service connection in the Cities of Union City and West New York.
Key Phases & Timeline
Sewer cleaning and CCTV beginning March and continuing into April. Sewer lining beginning in April.
Work Period & Location
Week of March 31st
Night work 3/31-4/4, 830pm setup active 9pm thru 5am:
- 12th Street between Morris St and up along Bergenline Ave to Tournade Lane
- Bergenline Ave between 42nd and 43rd street
- Bergenline Ave between 47th and 48th street
Description of Work
Cleaning and CCTV
Traffic Information:
Road Closures: Applicable roads will be closed overnight by police for the duration of active work at that location.
Parking Restrictions: None
Detours: Traffic will be reduced to a single lane in each direction during active construction.
Police presence: Yes, assisting with street closures as noted above.
Community Impacts
Noise/Disruptions: Sewer cleaning could produce some short duration noise.
We appreciate your patience and cooperation as we work to improve our infrastructure. Stay tuned for further updates!