NHSA H6/H7 Hoboken Phase 2 Construction and Traffic Management Activities: March 31st – April 4th, 202

Project Overview
We’re continuing Phase 2 of the H6/H7 Project to enhance infrastructure reliability and improve stormwater management in Hoboken. This work will support long-term system efficiency and reduce maintenance needs.

Key Phases & Timeline

  • Week of March 31st – April 4th, 2025

  • Work Locations:

    • 13th Street between Adams and Jefferson Streets

    • Adams Street between 13th and 15th Streets

Construction Activities

  • Working on louvers, pipe rails and painting for the pumps at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets

  • Installation of bollards, concrete curb, and sidewalk work under viaduct at the intersection of 14th and Adams Street

  • Installation of curbs and curb walls on 15th and Adams Streets

Traffic Management

  • Adams Street between 13th and 15th Streets will be closed to thru traffic for curb and sidewalk work, but open to thru traffic at night.

  • 15th Street will have one-way traffic going westbound towards Madison Street.

  • HPD officers will be present at all intersections.

  • 24/7 no parking signs will be in place on both sides of Adams Street between 13th and 15th Streets.

  • There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.

We appreciate your patience and cooperation as we work to improve our infrastructure.