Construction Activities and Traffic Management Update: NHSA H6/H7 Phase 2 Project in Hoboken May 6-10, 2024

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 05/06/2024 through 05/10/2024 is as follows:

 

Construction Activities

  • Installing Helical Anchors on Adams Street between 13th Street and 14th Street.

    • Note: Contractor will be using an excavator to install the anchors. Contractor will be performing noise monitoring throughout the Work.

 

Traffic Management

  • Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day from 5/6 thru 5/10.

  • 2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 13th, and one will be located at 14th. 

  • No parking signs will be placed on both sides of Adams Street between 13th Street and 14th Street from 5/6 thru 5/10.

  • There may be partial impacts to the sidewalks on Adams between 13th and 14th Streets in the Work area, however, safe passage for pedestrian traffic will be provided at all times.

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project Two-Week Look Ahead for May 13th to May 24th, 2024

Next
Next

Construction Update: North Hudson Sewerage Authority H6/H7 Phase 2 Project for Hoboken April 29, 2024 - May 3, 2024