Construction Update: North Hudson Sewerage Authority H6/H7 Phase 2 Project for Hoboken April 29, 2024 - May 3, 2024
Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 04/29/2024 through 05/03/2024 is as follows:
Construction Activities
Installing Helical Anchors on Adams Street between 13th Street and 14th Street.
Note: Contractor will be using an excavator to install the anchors. Contractor will be performing noise monitoring throughout the Work.
Traffic Management
Adams Street between 13th Street and 14th Street will be closed to thru traffic during the day from 4/30 thru 5/3.
2 HPD Officers will be present on site to assist in traffic redirection. One will be located at 13th, and one will be located at 14th.
No parking signs will be placed on both sides of Adams Street between 13th Street and 14th Street from 4/30 thru 5/3 between the hours of 6 AM to 6 PM. Contractor will not start Work until 8 AM.
There may be partial impacts to the sidewalks on Adams between 13th and 14th Streets in the Work area, however, safe passage for pedestrian traffic will be provided at all times.