Madison St. Area Infrastructure Improvements

STAGE 2 CONSTRUCTION ACTIVITY SCHEDULE: December 9th, 2024 – April 14th, 2025

Anticipated Overall Project Construction Schedule: October 2024 – May 2025

The Purpose of This Project:

The Madison Street Area Infrastructure Improvements project has been undertaken to mitigate localized flooding from rain events. To accomplish this, the project scope includes replacing existing inlets and sewer lines as well as elevating roadways, curbs, and sidewalks within the area. Ultimately, these improvements will alleviate the primary concerns by conveying the stormwater into the sewer system. Work to include:




  • Pile foundation installation to support utility lines such as sewer and water pipes.

  • Repaving all roadway construction and trench excavations.

  • Restoration of the construction site including full depth roadway reconstruction, as well as new sidewalks and street scape elements.

Traffic control will be coordinated with various projects in the surrounding area. Parking is to be restricted and road closures with detours is to be expected. To mitigate the traffic impacts from this closure, the flow of traffic on 11th Street between Jefferson St. and Monroe St. will be reversed during the construction period. Traffic on 11th Street currently travels in an easterly direction. Effective 8AM on Tuesday, January 14, 2025 the traffic will be reversed to flow in a westerly direction. Hoboken Police will be assisting with traffic coordination during this transition.

Location(s) Impacted by Construction:

  • Madison St between 10th St and 11th St

  • Intersection of 10th Street & Madison Street

 

Anticipated Construction Schedule:

Contractor will install new watermain and sanitary sewer on Madison St from 10th St to 11th St from December to April 2025. Below, you will see the estimated time frames for such work to commence and conclude, ultimately being subject to change. Restoration of roadways and sidewalks is expected to occur during the spring of 2025.

Construction Schedule Legend:

Stage 2 Construction Activity Schedule:

  • Madison St work between 10th St & 11th St including the intersection with 10th St: 12/9/24 – 04/14/25. Work Hours: 8:00 AM to 4:00 PM

A subsequent public notice will be issued for consequent project stages. Our Construction Manager for the project is Dewberry Engineers who can be reached with any questions at drocha@dewberry.com or (973)-576-9636

Who Should I Contact With Questions? If you have questions about work in your neighborhood, please visit www.nhudsonsa.com or contact dconger@nhudsonsa.com. Questions about construction can be directed to Grade Construction at (973) 925-4021. For immediate assistance, please contact our 24/7 Emergency Hotline at (866) 689-3970. 

Previous
Previous

North Hudson Sewerage Authority Weehawken Infrastructure Project for 1/13/2025

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project One Week look ahead for 1/6 - 1/10/2025