North Hudson Sewerage Authority Weehawken Infrastructure Project for 1/13/2025
One crew will be working on Highwood Ave and Hudson Pl.
Hamilton Ave Pump Station Crew
Monday 1/13/2025
• Asphalt & Concrete spot repair in on southeast corner of Hudson Pl & Highwood Ave.
House Keeping
• No vehicles, equipment, or materials will be stored on the sidewalk or in front of driveways.
• Weehawken PD will be onsite to provide traffic control as necessary
• Traffic signs to be posted as necessary.
Completed work:
Work has been completed on Blvd East from 700 Blvd East to Hamilton Ave. A new 48” PVC combined sewer was installed along with manholes and new laterals and cleanouts. Highwood Ave is complete, with new stormwater piping separating sewer and stormwater from Blvd East to Hudson Place. A stormwater force main was installed on Highwood Ave and connected to the pump station. Hudson Place also had new stormwater and sewer piping along with new catch basins and manholes. The pump station structure has been installed at the pump station location and the force main connection has been made. Pump station testing will be concluded in January 2025.