NHSA H6/H7 Hoboken Phase 2: Construction and Traffic Management Activities 01/13/2025 through 01/17/2025

Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 01/13/2025 through 01/17/2025 are as follows:

 

Construction Activities

  • Internal Piping Work and Stairs and Grating work at the NWRP Pump Station on 13th Street between Adams and Jefferson Street

  • Installation of Branch Connection between 14th and 15th Street

  • Installation of Underground Loop at Intersection of Adams and 15th Street

  • Installation of Concrete Piers and Pile caps at 15th Street

Traffic Management

  • HPD Officers will be present on site to assist in traffic redirection at all construction locations.

  • 24/7 no parking signs will be placed on both sides of Adams Street between 14th and 15thStreet.

  • There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.

  • Adams Street between 14th Street and 15th Street will be closed to thru traffic during the day.

  • 15th Street will have alternating traffic and tractor trailers and buses only.

Previous
Previous

NHSA H6/H7 Hoboken Phase 2: Construction and Traffic Management Activities 01/20/2025 through 01/24/2025

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project for 1/13/2025