NHSA H6/H7 Hoboken Phase 2: Construction and Traffic Management Activities 01/20/2025 through 01/24/2025

Holiday

  • 01/20/2025 – Martin Luther King Day – No Street Work for Contractor

 

Construction Activities

  • Internal Piping Work, Stairs and Grating work at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets

  • Installation of Branch Connection between 14th and 15th Streets

  • Installation of Underground Loop at Intersection of Adams and 15th Streets

  • Installation of Concrete Piers and Pile Caps on 15th Street between Adams and Grand Streets

 

Traffic Management

  • HPD Officers will be present on site to assist in traffic redirection at all construction locations.

  • 24/7 no parking signs will be placed on both sides of Adams Street between 14th and 15th Street.

  • There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.

  • Adams Street between 14th Street and 15th Street will be closed to thru traffic during the day.

  • 15th Street will have one-way traffic and tractor trailers, cars, and buses will be allowed through.

Next
Next

NHSA H6/H7 Hoboken Phase 2: Construction and Traffic Management Activities 01/13/2025 through 01/17/2025