Construction Activities
Working on Stairs, Grating and Prepping for Louvers at the NWRP Pump Station on 13th Street between Adams and Jefferson Streets
Installation of Branch Connection on Adams Street between 14th and 15th Streets
Installation of Concrete Piers and Pile Caps on 15th between Adams and Grand Streets
Traffic Management
HPD Officers will be present on site to assist in traffic redirection at all construction locations.
24/7 no parking signs will be placed on both sides of Adams Street between 14th and 15th Street.
There may be partial impacts to the sidewalks at 13th Street between Adams and Jefferson Streets within the pump station work area.
Adams Street between 14th Street and 15th Street will be closed to thru traffic during the day.
15th Street will have one-way traffic for all vehicles going west toward Madison Avenue.