Madison Street Area Infrastructure Improvements - Schedule Update (Week of 2/10/2025)
The Madison Street Area Infrastructure Improvements project is underway to address localized flooding from rain events. This comprehensive effort involves upgrading sewers, water lines, and stormwater infrastructure while elevating roadways, curbs, and sidewalks to better convey stormwater into the sewer system.
Construction Updates & Traffic Management
The following work and traffic activities are scheduled for Monday, February 10th through Friday, February 14th, 8 a.m. to 4 p.m.:
Work Activities:
Madison St between 10th and 11th Street:
Maintain sewer bypass
Excavate and install pile caps
Install new water main and sewer main
Continue installation of helical piles
Traffic Management:
Full closure of Madison St between 10th and 11th Street
No parking on Madison St between 10th and 11th Street
Hoboken Police Department (HPD) will be on-site to assist with traffic management
Please plan accordingly and follow posted detours and signage. NHSA appreciates your patience and cooperation as we work to enhance local infrastructure and reduce flooding risks in our community.