Anticipated Construction Activities and Traffic Management for the NHSA H6/H7 Phase 2 project for the period 12/18/2023 through 12/22/2023 is as follows:

Construction Activities

  • Test Pitting relating to the proposed Force Main installation at intersection of Adams Street and 13th Street.

  • Test Pitting relating to the proposed Force Main installation on Adams Street between 13th Street and 14th Street intersections.

  • Soil Sampling at intersection of Adams Street and 13th Street.

  • Soil Sampling on Adams Street between 13th Street and 14th Street intersections.

Traffic Management

o   Detour signs on Adams Street at 13th Street and 14th Street intersections.

o   Necessary parking spots shall be blocked off by the Parking Authority before Construction Activities begin.

o   Local, northbound traffic shall be directed by police officers in the area of Construction Activities.

o   Periodic lane shifts and/or lane closures on Adams Street at the 13th Street and 14th intersections. OEM will assist with traffic flow at this intersection for any closures

o   Periodic lane shifts and/or lane closures on Adams Street between 13th Street and 14th Street. OEM will assist with traffic flow at this intersection for any closures.

o   Per OEM request, both 13th Street and 14th Street intersections will not be closed at the same time to allow for northbound traffic. 

o   There may be partial impacts to the sidewalks, however, safe passage for pedestrian traffic will be provided at all times. 

o   Parking will be removed from 7 am – 5 pm between 13th and 14th. 

Previous
Previous

NHSA H6/H7 Phase 2 - Construction and Traffic Management Activities 12/26/2023 thru 12/29/2023

Next
Next

North Hudson Sewerage Authority Weehawken Infrastructure Project Two Week Look Ahead For 12/4 - 12/15/2023